Packing box room_ Steel structure hoisting process and specific hoisting scheme

2. The verticality of the column is controlled by measuring the distance between the inner side of the column and the cross control line on the building.

3. The adjustment of column height, axis and deflection is interrelated and balanced. Corrective work can only be completed if all criteria are met.

Section III assembly process of steel beam

Remove the steel beam near each column, transport it to the ground by truck crane, and then install it by mast crane. Headlamps with some heavy components can be lifted by truck crane. The secondary beam can be installed by self-made 5T tire crane. Starting from the third area, the main beam is first followed by the secondary beam, and then the screws. The steel beams are installed one by one by the mast crane according to the number. Only after the bolts are installed at both ends of the beam (or the spot welding is hard), the hook can be loosened, and then other steel beams can be lifted in turn. Welding after inspection.